About the Project
In an ongoing effort to provide quality wireless service, Verizon has identified your community as one that will benefit from improved network coverage.
Milestone Towers is proposing a wireless telecommunications facility at Rippon Station 15511 Farm Creek Dr, Woodbridge, VA 22191.
The proposal is for a 150-foot monopole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. Verizon will be the first wireless carrier to locate on the proposed tower.
Upcoming information:
Our Process
1. Due Diligence
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
2. Land Use
Special Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.
3. Permitting
Conduct Bid Walk With Contractors and school representatives, submit permit application, 60 Day Review Period
4. Construction
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.
5. Site Maintenance
Four visits per year for site maintenance | Remove trash, debris, check signage.
Annual RF testing | 2-4 visits per year for carrier modifications.